UNIVERSITY OF SHEFFIELD | WESTERN BANK LIBRARY
WESTERN BANK LIBRARY LEVEL 6
UNIVERSITY OF SHEFFIELD
PRINCIPAL CONTRACTOR
£300k
11 WEEKS
JCT INTERMEDIATE WITH CONTRACTORS DESIGN
LIBRARY SPACE REFURBISHMENT
ASSIX were appointed to fully refurbish this learning space on Level 6 of the Western Bank Library Building at the heart of the University Campus. The busy multistorey building remained occupied during the works which required careful planning and execution of the works to minimise disruption. The building also sits next to an important vehicle access road which meant additional management of vehicle & pedestrian movements while establishing a site compound.
Deliveries and waste removal had to be planned before 9 am and after 4.30 pm with access to our site compound was also constrained by weight restrictions for delivery vehicles (due to the location of subterranean lecture theatres existing on the approach road) and this was further complicated by security-controlled barriers which required us to pre-arrange vehicle access.
Material distribution and waste removal from the level 6 works area was via a fire escape stairwell and small goods lift which were shared by University students/staff for the duration of the contract and had to be maintained unobstructed at all times.
A robust approach to working/thorough inductions and regular briefing of operatives had to be undertaken throughout the project as the work area had multiple existing ACMs which had to be protected and left undisturbed by all construction operations.
The project scope of works included:
Demolition of existing walls and strip out of finishes/isolation and removal of all existing M&E installations had to be completed before commencing refurbishment works using a specialist licenced asbestos contractor with associated air monitoring.
Installation of new fire-rated stud walls to create a completely reconfigured space with interior glazed screens and dwarf walls segregating office areas, meeting rooms and circulation spaces.
New small power, lighting, security, data and fire alarm systems were installed to reflect the reconfigured space with AV installations to aid end-user functionality. A new MVHR system linked to BMS and local extract for WCs were installed including roof works to install a penthouse louvre installation for segregated vent exhaust.
Existing cast iron radiators were removed and refurbished/reinstalled using new LTHW distribution pipework and various other historic features were retained or replicated as was required as part of the grade 2 listing of this building.
Multiple work areas remote to the core level 6 works were also included in the project scope including the removal of existing and installation of new curtains to double height windows (circa 5.5m) where access was significantly restricted, decorations and replacement of floor finishes. This work had to be completed using a mixture of out-of-hours and co-ordinated attendance with the building management owing to the 24-hour use of the library facility.
COMPLETION PHOTOS
Assix were appointed as Principal Contractor on this two-phased listed building refurbishment project.
Assix were appointed as Principal Contractor for the refurbishment of levels 0 - 4 of the DICe Building which is located on Clarendon Street, Nottingham within the NTU City Campus.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2024
Working alongside the University of Sheffield to preserve and restore this important local landmark has been a tremendous privilege for ASSIX.
Assix were appointed as Principal Contractor for the refurbishment of Level 6 at the Western Bank Library building at the heart of the University Campus
Assix were appointed as Principal Contractor to complete this extensive facade refurbishment project for the University of Sheffield at their hexagonal Geography Building.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2023
Assix were appointed as Principal Contractor to complete the replacement of three large atrium rooflights for the University of Sheffield at the Hadfield CBE Building. The works were completed under the protection of weather tents while the building was occupied and involved extensive services works.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2022
Assix were appointed as Principal Contractor to complete a project of cast-iron heritage railing replacements and reconstruction of a listed retaining wall at Bartolome House.
Assix were appointed as Principal Contractor to complete the replacement of three large atrium rooflights for the University of Sheffield at the Hadfield CBE Building. The works were completed under the protection of weather tents while the building was occupied and involved extensive services works.
Assix were appointed as Principal Contractor following a competitive tender process to construct a new locker building for Derbyshire Police within the grounds of Ripley Police Station.
Assix were appointed as Principal Contractor to complete a large re-roofing project for the University of Sheffield at the Hadfield CBE Building. The complex works involved detailed phasing to maintain critical plant services within the building while facilitating the works.
Assix were appointed as Principal Contractor following a competitive tender process to carry out re-roofing to the Broad Lane Block housing the University’s Civil and Structural Engineering Department. The works were carried out above and within live teaching environments which required meticulously planned operations to complete the works safely and with minimal disruption. £600,000 project completed over 16 weeks.
Assix provided a full Construction Management service on this £325k car park extension & reconfiguration project for Univar & Ventgrove. The works in Bradford comprised extensive surface water drainage alongside new surfacing and electric vehicle charging point provision.
Assix completed Pre-Construction & Enabling Works Management Role for this £10m New Build Residential Project. Including development of project cost plan, programme & management of demolition and site remediation works.
Assix carefully delivered this office refurbishment project for an international chemical distributer in Wilmslow, Manchester.
Shell & Core Refurbishment of an 8 storey, 37,000 sq/ft city centre office building. Including roof repair, window refurbishment and concrete facade repairs.
Assix provided sub-contractor support services to take the Network Rail brief and translate into safe and workable solution in a rail workshop environment. Assix also provided estimating, procurement and change control management.
Assix provided sub-contractor support services to take London Underground brief and translate into safe and workable solution in rail workshop environement.
Assix provided sub-contractor support services to take the Network Rail brief and translate into safe and workable solution in a rail workshop environment. Assix also provided estimating, procurement and change control management.
The installation of a single storey double gable extension to provide new kitchen and garden room with existing kitchen and dining room subject to refurbishment to open up existing space and create a large dining and entertaining area